    Risk-based maintenance schedule of transmission line using multi-objective evolutionary algorithm

  • Author

    Li, Gaowang ; Shi, Dongyuan

  • Author_Institution
    Coll. of Electr. Eng. (CEEE), Huazhong Univ. of Sci. & Technol. (HUST), Wuhan, China
  • Volume
    1
  • fYear
    2011
  • fDate
    8-9 Sept. 2011
  • Firstpage
    413
  • Lastpage
    416
  • Abstract
    This paper describes a risk-based approach for multi-objective maintenance schedule of transmission line. A novel risk index is calculated by probabilistic load flow method, which accounts for the fluctuation of generator power, loads and transmission line´s outages. Elitist non-dominated sorting genetic algorithm (NSGA-II) is used to find the optimal solutions in large search space. The test results on the Roy Billinton Test System (RBTS) demonstrate the validity of the proposed approach.
  • Keywords
    genetic algorithms; maintenance engineering; power transmission lines; risk analysis; NSGA-II; RBTS; Roy Billinton Test System; multiobjective evolutionary algorithm; nondominated sorting genetic algorithm; probabilistic load flow method; risk-based maintenance schedule; transmission line; Biological cells; Load modeling; Maintenance engineering; Meteorology; Optimization; Power transmission lines; Schedules; Transmission line maintenance; multi-objective optimization; probabilistic load flow; risk assessment;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Power Engineering and Automation Conference (PEAM), 2011 IEEE
  • Conference_Location
    Wuhan
  • Print_ISBN
    978-1-4244-9691-4
  • Type

    conf

  • DOI
    10.1109/PEAM.2011.6134883
  • Filename
    6134883