• DocumentCode
    3100954
  • Title

    Inclusion of Wind in the MISO Transmission Expansion Planning Process

  • Author

    Osborn, Dale ; Wilson, J.L.

  • Author_Institution
    Midwest ISO, Carmel, IN
  • fYear
    2007
  • fDate
    24-28 June 2007
  • Firstpage
    1
  • Lastpage
    4
  • Abstract
    The Midwest ISO performs exploratory studies to determine information about the combined generation and transmission system operating the Eastern Interconnection and the Joint and Common Market with PJM. The example in this paper is a simulation of the power system in the year 2016 with 16,000 MW of wind generation added to a MISO and PJM wide 765 kV transmission system. High Surge Impedance Loading design transmission parameters are used to model the 765 kV expansion. Results show that the wind generation would displace about 43 M tons of carbon dioxide from coal, gas and other fuels. The economics amount to roughly a break even proposition if the subsequent benefits could be distributed properly.
  • Keywords
    power system interconnection; power transmission planning; wind power plants; Eastern interconnection; MISO expansion planning process; Midwest Independent Transmission System Operator; high surge impedance loading design; power 16000 MW; power system; voltage 765 kV; wind generation; wind inclusion; ISO; Power generation; Power system interconnection; Power system modeling; Power system planning; Power system simulation; Process planning; Surges; Wind energy generation; Wind power generation; 765kV; High Surge Impedance Loading; Midwest ISO; PJM; Vision Exploratory Study;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Power Engineering Society General Meeting, 2007. IEEE
  • Conference_Location
    Tampa, FL
  • ISSN
    1932-5517
  • Print_ISBN
    1-4244-1296-X
  • Electronic_ISBN
    1932-5517
  • Type

    conf

  • DOI
    10.1109/PES.2007.386059
  • Filename
    4275825