Abstract :
Crane-beam on rock wall is an integrated construction technology containing smooth presplit blasting, anchor technique, concrete technology, stress, strain and displacement measurement technology. Crane-beam on rock wall is a key project in underground powerhouse engineering and is well worth discussing in effective economical construction. In this paper, excavation of crane-beam on rock wall and concrete construction had been introduced in detail on power generation systems in underground powerhouse of Longtan Hydropower Station. Crane-beam on rock wall contains a number of steel and has a complex geological conditions, complex steel structure, high technical requirement and difficult construction. Correct construction procedure and technology is the key to ensure quality of construction.
Keywords :
anchors; beams (structures); cranes; excavators; rocks; steel; walls; Longtan hydropower station; anchor technique; complex steel structure; concrete technology; crane-beam construction; excavation; integrated construction technology; power generation systems; presplit blasting; rock wall; underground powerhouse; Concrete; Displacement measurement; Hydroelectric power generation; Rocks; Space stations; Steel; Water resources; Crane-beam on rock wall; construction procedure and technology; security detection; temperature control;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Consumer Electronics, Communications and Networks (CECNet), 2011 International Conference on
Conference_Location :
XianNing
Print_ISBN :
978-1-61284-458-9
Type :
conf
DOI :
10.1109/CECNET.2011.5768523
Filename :
5768523
Link To Document :
بازگشت