Abstract :
National Grid has been installing Numerical Busbar Protection (BBP) systems at its 400 kV, 275 kV and 132 kV double busbar substations for approximately ten years. This Paper investigates the design, operational and lifetime management experiences/challenges associated with moving to these solutions. The paper will consider these challenges under the following five categories: (1) Policy and application design (2) Operational experience to date (3) Contingency plans following unavailability (4) Spares holding and post commissioning support (5)Extendibility, Compatibility and Asset Life.
Keywords :
busbars; power grids; power transmission protection; double busbar substations; national grid; numerical busbar protection systems; transmission utility experience; voltage 132 kV; voltage 275 kV; voltage 400 kV; Numerical Busbar Protection; Transmission Utility Experience;
fLanguage :
English
Publisher :
iet
Conference_Titel :
Developments in Power System Protection (DPSP 2010). Managing the Change, 10th IET International Conference on
Conference_Location :
Manchester
Type :
conf
DOI :
10.1049/cp.2010.0221
Filename :
5522235
Link To Document :
بازگشت