Abstract :
The Spallation Neutron Source accelerator systems will deliver a 1.0 GeV, 1.4 MW proton beam to a liquid mercury target for neutron scattering research. The staged beam commissioning of the accelerator complex is proceeding as component installation progresses. The Front End, Drift Tube Linac and three of the four Coupled-Cavity Linac modules have been commissioned with beam at ORNL. Results and status of the beam commissioning program are presented.
Keywords :
Acceleration; Current measurement; Ion sources; Laboratories; Linear accelerators; Linear particle accelerator; Neutrons; Optical coupling; Particle beams; Proton accelerators;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Particle Accelerator Conference, 2005. PAC 2005. Proceedings of the
Print_ISBN :
0-7803-8859-3
Type :
conf
DOI :
10.1109/PAC.2005.1590369
Filename :
1590369
Link To Document :
بازگشت