Commissioning of the LHC Beam Transfer Line TI 8
Author :
Uythoven, J. ; Arduini, G. ; Goddard, B. ; Jacquet, D. ; Kain, V. ; Lamont, M. ; Mertens, V. ; Spinks, A. ; Wenninger, J. ; Chao, Y.
Author_Institution :
CERN, Geneva, Switzerland
fYear :
2005
fDate :
16-20 May 2005
Firstpage :
1461
Lastpage :
1463
Abstract :
The first of the two LHC transfer lines was commissioned in autumn 2004. Beam reached an absorber block located some 2.5 km downstream of the SPS extraction point at the first shot, without the need of any threading. The hardware preparation and commissioning phase will be summarised, followed by a description of the beam tests and their results regarding optics and other line parameters, including the experience gained with beam instrumentation, the control system and the machine protection equipment.
Keywords :
Adders; Circuit testing; Control systems; Cooling; Hardware; Large Hadron Collider; Magnets; Software testing; System testing; Temperature measurement;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Particle Accelerator Conference, 2005. PAC 2005. Proceedings of the
Print_ISBN :
0-7803-8859-3
Type :
conf
DOI :
10.1109/PAC.2005.1590798
Filename :
1590798
Link To Document :
بازگشت