  • Title

    Installation and Testing for Commissioning of Normal Conducting RF Linac Segment in the SNS

  • Author

    Kang, Y. ; Aleksandrov, A. ; Anderson, D. ; Champion, M.M. ; Champion, M.S. ; Crofford, M. ; Deibele, C. ; Dodson, G. ; Fuja, R. ; Gibson, P. ; Gurd, P. ; Hardek, T. ; Johnson, G. ; Ladd, P. ; Ma, H. ; McCarthy, M. ; Piller, M. ; Tang, J. ; Vassioutchenko

  • Author_Institution
    ORNL, TN, USA
  • fYear
    2005
  • fDate
    16-20 May 2005
  • Firstpage
    2571
  • Lastpage
    2573
  • Abstract
    The Spallation Neutron Source (SNS) linac will deliver a 1.0 GeV proton beam to its accumulator ring. The normal conducting segment of the linac has a radio frequency quadrupole (RFQ), six drift tube linac (DTL) tanks powered by seven 402.5 MHz klystrons and four coupled cavity linac (CCL) modules powered by four 805 MHz klystrons that deliver the 180 MeV beam to the superconducting section of the linac (SCL) that employs eighty one 6-cell cavities powered by eighty-one 805 MHz klystrons. The normal conducting accelerating linac segment has been completely installed in the linac tunnel and successfully conditioned and commissioned. Corresponding high voltage converter modulator (HVCM) and low level RF (LLRF) control systems have been installed and tested.
  • Keywords
    Acceleration; Klystrons; Linear particle accelerator; Neutrons; Optical coupling; Particle beams; Radio frequency; Superconducting devices; Testing; Voltage control;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Particle Accelerator Conference, 2005. PAC 2005. Proceedings of the
  • Print_ISBN
    0-7803-8859-3
  • Type

    conf

  • DOI
    10.1109/PAC.2005.1591186
  • Filename
    1591186