DocumentCode :
330849
Title :
Reducing costs and increasing throughput using model-based process control on sputtering systems
Author :
Sattler, Linda ; Hecker, Phil E. ; Raghavan, Rangesh ; Lin, He
Author_Institution :
Nat. Microelectron. Res. Centre, Univ. Coll. Cork, Ireland
fYear :
1998
fDate :
19-21 Oct 1998
Firstpage :
409
Lastpage :
414
Abstract :
As the target within a sputter system erodes over time, the deposition rate decreases. In mass production semiconductor facilities, the sputter process is usually controlled by using monitor wafers and adjusting the deposition time or power to obtain a constant thickness. By modeling deposition rates with regard to target life, these costly monitor wafers can be removed; thereby increasing available time for product wafers. Using over a year of production data on the numerous sputter tools in several of Texas Instruments´ fabrication plants, quadratic models of AlCu and Ti deposition rates have been developed. These models, along with simple operator procedure and software changes, were implemented at one fab in less than six months with no added costs. Furthermore, the identified monitor wafer savings at all of Texas Instruments´ fabs account for a 79% reduction in pilot usage with a potential 4.9% capacity increase. Process control has also shown significant improvements
Keywords :
cost-benefit analysis; integrated circuit interconnections; integrated circuit metallisation; integrated circuit reliability; integrated circuit yield; model reference adaptive control systems; process control; process monitoring; semiconductor process modelling; sputter deposition; AlCu; AlCu deposition models; Ti; Ti deposition models; cost reduction; deposition power; deposition rate; deposition rate modelling; deposition thickness; deposition time; mass production semiconductor facilities; model-based process control; monitor wafer savings; monitor wafers; operator procedure; pilot wafer usage; process control; product wafers; production data; quadratic models; sputter process control; sputter system target erosion; sputter tools; sputtering systems; target life; throughput; wafer capacity; Costs; Instruments; Mass production; Monitoring; Power system modeling; Process control; Semiconductor device modeling; Thickness control; Throughput; Weight control;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Electronics Manufacturing Technology Symposium, 1998. Twenty-Third IEEE/CPMT
Conference_Location :
Austin, TX
ISSN :
1089-8190
Print_ISBN :
0-7803-4523-1
Type :
conf
DOI :
10.1109/IEMT.1998.731166
Filename :
731166
Link To Document :
بازگشت