Title :
Reliability and economic based analysis to determine an opportune rehabilitation and modernization schedule for hydroelectric facilities
Author :
Holbert, K.E. ; Ogeuk Kwon
Author_Institution :
Sch. of Electr., Comput. & Energy Eng., Arizona State Univ., Tempe, AZ, USA
fYear :
2011
fDate :
4-6 Aug. 2011
Firstpage :
1
Lastpage :
6
Abstract :
Twenty-four synchronous generators and associated equipment are selected to represent hydroelectric equipment reliability and system availability. Fault data for the 24 generators are collected and filtered for only forced outage data, from which equipment reliabilities are determined. The eight major equipments in a hydropower plant are divided into two groups based on their reliability for calculation of rehabilitation and modernization timing. Considering reliability and economics, it appears that 20 to 23 years is a favorable time to rehabilitate equipment of group 2, which includes the switchyard circuit breaker (CB), excitation system, governor and main CB, and 40 to 45 years is an opportune time to modernize group 1 equipment, comprised of the rotor, stator, turbine and main transformer.
Keywords :
circuit breakers; hydroelectric power stations; power system management; power system reliability; synchronous generators; economic based analysis; fault data; hydroelectric equipment reliability; hydroelectric facilities; hydropower plant; main transformer; modernization schedule; opportune rehabilitation; rotor; stator; switchyard circuit breaker; synchronous generators; system availability; turbine; Circuit breakers; Circuit faults; Hydroelectric power generation; Reliability; Rotors; Stators;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
North American Power Symposium (NAPS), 2011
Conference_Location :
Boston, MA
Print_ISBN :
978-1-4577-0417-8
Electronic_ISBN :
978-1-4577-0418-5
Type :
conf
DOI :
10.1109/NAPS.2011.6024853
Filename :
6024853
Link To Document :
بازگشت