Title :
A study on ESS installation Order for SeoulMetro lines
Author_Institution :
Adv. EMU Res. Team, Korea Railroad Res. Inst., Uiwang, South Korea
Abstract :
If the ESSs are installed on Line 2~4, we will obtain 16% of energy saving rate and average 4year of ROI. We analyze which substation will be the first order to be installed. The energy saving rate order and the ROI order are different. Even if the energy saving rate is low, because the quantity of regenerative energy is a lot, the ROI is short. Therefore, we have to choose the ROI instead of the energy saving rate to install the ESS. Because the rail operating companies do not have many budget, companies have to install in order from the substation of high energy saving rate to the substation of a little bit high energy saving rate.
Keywords :
energy storage; railway engineering; substations; ROI; SeoulMetro lines; energy saving rate order; energy storage system installation order; regenerative energy; substation; Acceleration; Vehicles;
Conference_Titel :
Circuits and Systems (MWSCAS), 2011 IEEE 54th International Midwest Symposium on
Conference_Location :
Seoul
Print_ISBN :
978-1-61284-856-3
Electronic_ISBN :
1548-3746
DOI :
10.1109/MWSCAS.2011.6026556