Chronological probabilistic production costing and wheeling calculations with transmission network modeling
Author
Pereira, M.V.F. ; Gorenstin, B.G. ; Morozowski, M. ; Silva, J.B.
Author_Institution
CEPEL, Rio de Janeiro, Brazil
fYear
1991
fDate
7-10 May 1991
Firstpage
70
Lastpage
76
Abstract
An approach for the integrated analysis of generation and transmission systems in terms of production costing and wheeling rate calculation is presented. The methodology is based on the chronological simulation of system operation. Economic dispatch at each state is provided by linearized optimal power flow routines, which can represent network aspects and export/import contracts among utilities. Probabilistic aspects are represented by Monte Carlo sampling of generation capacities, load levels, etc. Marginal costs are calculated at bus level, and serve as a basis for the evaluation of wheeling rates. This makes it possible to model complex utility situations for use in power system planning and operations, determination of interchange contracts, and regulatory applications
Keywords
Monte Carlo methods; digital simulation; economics; load dispatching; load flow; optimisation; power system analysis computing; power system planning; probability; transmission networks; Monte Carlo sampling; chronological simulation; economics; generation; linearized optimal power flow; load dispatching; load flow; power system analysis computing; power system planning; probabilistic production costing; transmission network modeling; wheeling; Capacity planning; Contracts; Costing; Costs; Load flow; Monte Carlo methods; Power generation economics; Power system economics; Power system modeling; Production systems;
fLanguage
English
Publisher
ieee
Conference_Titel
Power Industry Computer Application Conference, 1991. Conference Proceedings
Conference_Location
Baltimore, MD
Print_ISBN
0-87942-620-9
Type
conf
DOI
10.1109/PICA.1991.160657
Filename
160657
Link To Document