DocumentCode :
3484294
Title :
Problems of putting into operation generating reserves of the power system during frequency deviation
Author :
Chuvychin, V. ; Gurov, N. ; Rubcov, S. ; Strelkovs, V.
Author_Institution :
Riga Tech. Univ., Riga
fYear :
2005
fDate :
27-30 June 2005
Firstpage :
1
Lastpage :
5
Abstract :
Paper considers problems of frequency control during power system islanding using as an example the joint electric power system of the Baltic States. Existing frequency actuated emergency automation system is non-adaptive to the variety of emergency situations. New mode for determination of deficiency value in the islanded power system is suggested to control generating reserves actuation. Results of mathematical simulation of frequency control are presented.
Keywords :
distributed power generation; frequency control; power generation control; power system interconnection; Baltic States; emergency automation system; frequency control; frequency deviation; joint electric power system; Automation; Frequency control; Power generation; Power system analysis computing; Power system control; Power system interconnection; Power system modeling; Power system restoration; Power system stability; Power systems; Frequency control; modeling; power system;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Power Tech, 2005 IEEE Russia
Conference_Location :
St. Petersburg
Print_ISBN :
978-5-93208-034-4
Electronic_ISBN :
978-5-93208-034-4
Type :
conf
DOI :
10.1109/PTC.2005.4524555
Filename :
4524555
Link To Document :
بازگشت