DocumentCode
3498195
Title
On-site testing of gas insulated substation with AC voltage
Author
Gamlin, M. ; Rickmann, J. ; Schikarski, P. ; Feger, H. ; Feser, K.
Author_Institution
Haefely Trench, Basel, Switzerland
Volume
5
fYear
1999
fDate
1999
Firstpage
232
Abstract
Experience has proven that the reliability of a GIS/GIL can be ensured by an on-site AC-testing after assembly combined with a sensitive partial discharge measurement. Either conventional 50/60 Hz transformer systems or resonant test systems with variable inductance as well as resonant test systems with variable frequency have been used to perform the GIS/GIL on-site testing. The paper describes the different HV test systems with their advantages and limitations and the applicable partial discharge measuring methods. The UHF PD measuring method is emphasised
Keywords
gas insulated substations; 50 Hz; 60 Hz; AC voltage; GIS; HV test systems; UHF PD measuring method; gas insulated lines; gas insulated substation; on-site testing; partial discharge measuring methods; resonant test systems; sensitive partial discharge measurement; variable inductance;
fLanguage
English
Publisher
iet
Conference_Titel
High Voltage Engineering, 1999. Eleventh International Symposium on (Conf. Publ. No. 467)
Conference_Location
London
ISSN
0537-9989
Print_ISBN
0-85296-719-5
Type
conf
DOI
10.1049/cp:19990928