Abstract :
Describes a study of the various risk factors on tunnel boring machine (TBM) and their differing impacts on cost and time. It has been concluded that it is important to make a clear distinction between normal cost and time, and the risk events that cause exceptional cost and time. The budget and tender price can be determined separately, both by the client and contractor respectively. To meet the demands placed on decision making for tender and procurement for currently favored construction-contracting methods, a new model for estimating tender price and budget has been developed, and is described in this paper. The predictions obtained from the estimation model are shown to be realistic, as the total construction cost and time obtained from the model correspond fairly well to the actual construction cost and time. The separate estimation of normal cost and time and exceptional cost and time contribute to the clarity of the results.
Keywords :
boring machines; budgeting; construction; decision making; pricing; procurement; risk analysis; tendering; tunnels; TBM; budget price; cost modeling; decision making; decision-aid estimation models; favored construction-contracting methods; procurement; risk evaluation; risk events; tender price; time modeling; tunnel boring machine; Cost function; Decision making; Information technology; Machine intelligence; Predictive models; Procurement; Risk management; Stochastic processes; Technology management; Tunneling;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Intelligent Information Technology Application Workshops, 2009. IITAW '09. Third International Symposium on
Conference_Location :
Nanchang
Print_ISBN :
978-1-4244-6420-3
Electronic_ISBN :
978-1-4244-6421-0
Type :
conf
DOI :
10.1109/IITAW.2009.129
Filename :
5419461
Link To Document :
بازگشت