In this work we deal with a resource constrained project scheduling problem. The considered activities represent tasks in a manufacturing assembly process, in which multiple copies of a certain product have to be created. For each copy of the product, the operations must be processed on dedicated machines and must satisfy a given set of precedence constraints. The objective is to minimise the overall make span. When the number of copies becomes large, we are interested in designing periodic (or cyclic) schedules, where we want to maximize throughput, i.e., number of copies produced in a time unit, while keeping product flow time low. We present a heuristic algorithm based on a branch and bound scheme for the case of a pipeline assembly process.
Keywords
assembling; computational complexity; minimisation; project management; scheduling; tree searching; branch-and-bound scheme; cyclic schedule; heuristic algorithm; makespan minimization; manufacturing assembly process; pipeline assembly process; precedence constraint; resource constrained project scheduling problem; Assembly; Heuristic algorithms; Job shop scheduling; Schedules; Throughput; Heuristic Algorithms; Manufacturing Assembly Systems; Scheduling; Tasks Precedences;
fLanguage
English
Publisher
ieee
Conference_Titel
Computer Modelling and Simulation (UKSim), 2014 UKSim-AMSS 16th International Conference on
Print_ISBN
978-1-4799-4923-6
Type
conf
DOI
10.1109/UKSim.2014.41
Filename
7046067
Link To Document