DocumentCode
3581125
Title
An optimized planning model for black-start units considering CCHP systems as start units
Author
Xiaobin Guo ; Zhan Shen ; Jinyong Lei ; Xu Chen ; Shan Lin ; Yi Sun ; Zhaoxia Jing
Author_Institution
Smart Grid Inst., Sci. Res. Inst. of China, Guangzhou, China
fYear
2014
Firstpage
1
Lastpage
5
Abstract
CCHP (combined cooling, heating and power) systems have good performance as black-start units. It is the most important black-start unit in areas which do not have hydro power units. In this paper, the CCHP system is designed and planned under extra consideration of it serving as a black-start unit. It puts forward an optimized planning (allocation) model for CCHP systems with the consideration of CCHP systems being black-start units. Based on the regional black-start units, black-start schemes and load conditions, the reliability of black-start, outage cost and investment on construction are calculated. Aiming to minimize outage cost and investment on construction, setting simulation results as constraints, building the optimized model and finally applying the Particle Swarm Optimization (PSO) method to attain the best solution. The analysis of example case indicates that the optimized planning proposed here is effective. It gives important reference for the design and planning of CCHP system.
Keywords
cogeneration; cooling; particle swarm optimisation; power generation planning; power generation reliability; CCHP system design; PSO method; black-start unit reliability; combined cooling heating and power system; optimized planning model; outage cost minimization; particle swarm optimization method; start units; Generators; Investment; Load modeling; Planning; Power transmission lines; Reliability; CCHP system; Particle Swarm Optimization (PSO); black-start unit; optimal allocation;
fLanguage
English
Publisher
ieee
Conference_Titel
Power and Energy Engineering Conference (APPEEC), 2014 IEEE PES Asia-Pacific
Type
conf
DOI
10.1109/APPEEC.2014.7066141