Title :
Overall challenges and recommendations concerning the integration of small scale hydro in MV distribution networks
Author :
Henning Taxt;Maria Daniela Catrinu;Dag Eirik Nordgård
Author_Institution :
Energy Res., SINTEF, Trondheim, Norway
fYear :
2013
fDate :
6/1/2013 12:00:00 AM
Firstpage :
1
Lastpage :
4
Abstract :
Norwegian distribution companies are currently experiencing that the connection of small hydropower plants to distribution networks is causing problems due to limited transfer capacity in the existing grids and violation of voltage quality threshold values. The situation is expected to escalate in the future when the number of new units will increase considerably due to favourable incentives for investing in renewable generation. This paper discusses the overall challenges and network solutions to support new DG connections.
Publisher :
iet
Conference_Titel :
Electricity Distribution (CIRED 2013), 22nd International Conference and Exhibition on
Type :
conf
DOI :
10.1049/cp.2013.0986
Filename :
6683589
Link To Document :
بازگشت