The Spallation Neutron Source (SNS) accelerator systems will provide a 1 GeV, 1.44 MW proton beam to a liquid mercury target for neutron production. In order to satisfy the accelerator systems´ portion of the critical decision 4 (CD-4) commissioning goal (which marks the completion of the construction phase of the project), a beam pulse with intensity greater than 1×1013 protons must be accumulated in the ring, extracted in a single turn and delivered to the target. A commissioning plan has been formulated for bringing into operation and establishing nominal operating conditions for the various ring and transport line subsystems as well as for establishing beam conditions and parameters which meet the commissioning goal.
Keywords :
linear accelerators; liquid metals; mercury (metal); neutron sources; proton beams; storage rings; Hg; Spallation Neutron Source ring; accelerator systems; beam pulse; commissioning plan; liquid mercury target; neutron production; proton beam; transport lines; Fires; Hardware; Laboratories; Linear accelerators; Linear particle accelerator; Neutrons; Particle beams; Production; Proton accelerators;
Conference_Titel :
Particle Accelerator Conference, 2003. PAC 2003. Proceedings of the
Print_ISBN :
0-7803-7738-9
DOI :
10.1109/PAC.2003.1288597