• DocumentCode
    41793
  • Title

    Look Ahead Robust Scheduling of Wind-Thermal System With Considering Natural Gas Congestion

  • Author

    Cong Liu ; Changhyeok Lee ; Shahidehpour, Mohammad

  • Author_Institution
    Decision & Inf. Sci., Argonne Nat. Lab., Argonne, IL, USA
  • Volume
    30
  • Issue
    1
  • fYear
    2015
  • fDate
    Jan. 2015
  • Firstpage
    544
  • Lastpage
    545
  • Abstract
    Natural gas pipeline congestion will impact on the fuel adequacy of several natural gas fired generating units at the same time. This letter focuses on the development of a robust optimization methodology for the scheduling of quick start units when considering natural gas resource availability constraints. Natural gas transmission will be approximated by linear constraints, and the linepack capacity of pipelines will be considered in the proposed model. Case studies show the effectiveness of the proposed model and algorithms.
  • Keywords
    natural gas technology; optimisation; pipelines; power generation scheduling; thermal power stations; wind power plants; look ahead robust scheduling; natural gas congestion; natural gas fired generating units; natural gas pipeline congestion; natural gas resource availability constraints; natural gas transmission; wind-thermal system; Mathematical model; Optimization; Pipelines; Processor scheduling; Robustness; Uncertainty; Natural gas electric coordination; renewable energy; robust optimization; unit commitment;
  • fLanguage
    English
  • Journal_Title
    Power Systems, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0885-8950
  • Type

    jour

  • DOI
    10.1109/TPWRS.2014.2326981
  • Filename
    6827255