DocumentCode
619816
Title
Application of the steepest descent approximate linear programming on cyclic cleaning scheduling of boiler
Author
Liu Pingping ; Ma Xin ; Gao Dong ; Zhang Beike
Author_Institution
Coll. of Inf. Sci. & Technol., Beijing Univ. of Chem. Technol., Beijing, China
fYear
2013
fDate
25-27 May 2013
Firstpage
869
Lastpage
874
Abstract
Traditional approximate linear programming may exclude the optimal solution out of the boundary condition, which is caused by the subjective choices of initial feasible point, step restriction and reduction coefficient. In this paper, a method called steepest descent-approximate linear programming is presented which redefines the judgment conditions and the way of boundary adjustment based on the purposeful search and rapid convergence from steepest descent method, where the boundary directions are adjusted together by the nonlinear constraint satisfaction degree and the current objective function. Besides absorbing the original advantages of easy implementation and convenient solution from traditional approximate linear programming, the new method can not only eliminate the negative impact which is caused by subjective choices of step restriction and reduction coefficient, but also solve a nonlinear programming problem which only contains linear constraints. The method has been applied in a real thermal power plant, for which a mathematical model for the solution of the cyclic cleaning scheduling problem of boiler system with decaying performance is built and optimized. Moreover, the usefulness of the method shows it achieves remarkable energy saving compared with the original approaches.
Keywords
approximation theory; boilers; energy conservation; linear programming; nonlinear programming; power system management; scheduling; thermal power stations; boiler; boundary adjustment; boundary condition; cyclic cleaning scheduling; energy saving; nonlinear constraint satisfaction degree; objective function; reduction coefficient; steepest descent approximate linear programming method; steepest descent method; step restriction; thermal power plant; Boilers; Boundary conditions; Cleaning; Linear programming; Programming; Redundancy; Vectors; Cyclic Cleaning Scheduling of Boiler; Nonlinear Programming; Steepest Descent Approximate Linear Programming;
fLanguage
English
Publisher
ieee
Conference_Titel
Control and Decision Conference (CCDC), 2013 25th Chinese
Conference_Location
Guiyang
Print_ISBN
978-1-4673-5533-9
Type
conf
DOI
10.1109/CCDC.2013.6561045