Title :
Progress of developing the 10MW L-band multi-beam klystron
Author :
Yong Wang ; Rui Zhang ; Junjie Fan ; Yong Zhong ; Wenxin Liu
Author_Institution :
Key Lab. of High Power Microwave Sources & Technol., Inst. of Electron., Beijing, China
Abstract :
The Development of the 10MW L-band multibeam klystron was started in the Institute of Electronics, Chinese Academy of Sciences (IECAS) three years ago. The electrical and structural designs for this klystron have been accomplished , in which many technical problems have been resolved. In the design of electron optical system, the uniform field multiple-lens focusing scheme was adopted, by which the paraxial multi-beams with good laminarity and fluctuation were obtained. In the design of beam-wave interaction system, the second harmonic cavity was used to enhance the beam-wave interaction efficiency and reduce the volume and weight of the klystron. Nowadays, the prototype is being fabricated and will be finished in one or two months. This paper presents the research progress on the 10MW L-band multi-beam klystron and the key technical issues resolved in detail.
Keywords :
electron lenses; electron optics; klystrons; optical focusing; IECAS; Institute of Electronics, Chinese Academy of Sciences; L-band multibeam klystron; beam-wave interaction system; electron optical system; laminarity; paraxial multibeam; power 10 MW; second harmonic cavity; uniform field multiple-lens focusing scheme; Cathodes; Cavity resonators; Focusing; Klystrons; L-band; Laser beams; Prototypes; 10MW; L-band; multi-beam klystron; research progress;
Conference_Titel :
Vacuum Electronics Conference (IVEC), 2013 IEEE 14th International
Conference_Location :
Paris
Print_ISBN :
978-1-4673-5976-4
DOI :
10.1109/IVEC.2013.6570926