Title :
Overview of the 500MW EirGrid East-West Interconnector, considering System Design and execution-phase issues
Author :
Egan, J. ; O´Rourke, P. ; Sellick, R. ; Tomlinson, P. ; Johnson, B. ; Svensson, S.
Author_Institution :
EirGrid Plc, Dublin, Ireland
Abstract :
The EirGrid East-West Interconnector between Ireland and Wales, which uses ABB´s HVDC Light® Voltage-Sourced Converter (VSC) technology, is to date the world´s most powerful VSC scheme, it is the first commercial VSC project connected to Ireland, and it is the first HVDC Light® scheme to use ±200kV cables. Ireland has plans to expand wind power generation and the link will facilitate the addition of renewables and provide the possibility to export or import energy to / from the UK market. The new link also enhances security of supply in the Irish grid, allows both Ireland and the UK access to more competition and provides black-start capabilities. This paper presents an overview of the EirGrid East-West Interconnector project, considering the Converter topology, System Design, Overview of the VSC technology used, and some of the significant execution-phase site works issues.
Keywords :
HVDC power convertors; power cables; power grids; power system interconnection; wind power plants; ABB HVDC light voltage-sourced converter; EirGrid East-West interconnector project; Ireland; Irish grid; UK market; VSC technology; Wales; black-start capability; execution-phase; power 500 MW; power cables; supply security; system design; wind power generation; Cable insulation; Electricity; HVDC transmission; Integrated circuit interconnections; Power conversion; Topology; Cable Installation; HVDC Light; VSC;
Conference_Titel :
Power Engineering Conference (UPEC), 2013 48th International Universities'
Conference_Location :
Dublin
DOI :
10.1109/UPEC.2013.6714867