    Combining sectional processing algorithm and compound incremental cost based list scheduling algorithm for long-horizon job-shop scheduling problems

  • Author

    Shin-Yeu Lin ; Jui-Yen Cheng

  • Author_Institution
    Dept. of Electr. & Control Eng., Nat. Chiao Tung Univ., Hsinchu, Taiwan
  • fYear
    2001
  • fDate
    4-7 Sept. 2001
  • Firstpage
    1029
  • Lastpage
    1033
  • Abstract
    In this paper, we combine the sectional processing algorithm with the compound incremental cost based list scheduling algorithm to solve long-horizon job-shop scheduling problems. Our algorithm has achieved the reduction of both CPU times and objective values in comparing with the original method. In our simulation results, we observe that when the section length of our algorithm approximately equals the average system time, the reduction of both CPU times and objective values are approximately optimal. This observation leads us to proposing a receding horizon scheduling algorithm for infinite-horizon job-shop scheduling problems. This algorithm allows us to solve the scheduling problem one section at a time. Thus, it will not only save the computation time tremendously but also easily take care of the variation of the system configuration.
  • Keywords
    job shop scheduling; optimisation; CPU time reduction; average system time; compound incremental cost based list scheduling algorithm; infinite-horizon job-shop scheduling problem; long-horizon job-shop scheduling problems; objective value reduction; receding horizon scheduling algorithm; sectional processing algorithm; system configuration; Europe; Job-shop scheduling; Lagrange relaxation method; heuristic algorithm; optimization; receding horizon;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Control Conference (ECC), 2001 European
  • Conference_Location
    Porto
  • Print_ISBN
    978-3-9524173-6-2
  • Type

    conf

  • Filename
    7076049