Contribution to load-frequency regulation of a hydropower plant with long tail-race tunnel
Author :
Martinez-Lucas, Guillermo ; Sarasua, Jose Ignacio ; Wilhelmi, Jose Roman ; Sanchez, Jose Angel
Author_Institution :
Dept. of Hydraulic, Energy & Environ. Eng., Tech. Univ. of Madrid (UPM), Madrid, Spain
fYear :
2015
fDate :
10-13 June 2015
Firstpage :
1886
Lastpage :
1891
Abstract :
In this paper, a hydroelectric power plant with long tail-race tunnel has been modelled for assessing its contribution to secondary regulation reserve. Cavitation problems, caused by the discharge conduit length, are expected downstream the turbine where low pressure appears during regulation manoeuvres. Therefore, governor´s gains should be selected taking into account these phenomena. On the other hand, regulation services bidden by the plant operator should fulfil TSO (Transmission System Operator) quality requirements. A methodology for tuning governor PI gains is proposed and applied to a Hydro power plant in pre-design phase in northwest area of Spain. The PI gains adjustment proposed provides a proper plant response, according to some established indexes, while avoiding cavitation phenomena.
Keywords :
frequency control; hydroelectric power stations; load regulation; turbines; PI gain; Spain; TSO; discharge conduit length; hydroelectric power plant; load-frequency regulation; long tail-race tunnel; plant response; regulation manoeuvre; transmission system operator; turbine; Automatic generation control; Frequency control; Hydraulic turbines; Load modeling; Mathematical model; cavitation; hydropower generation; load-frequency control; long tail-race;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Environment and Electrical Engineering (EEEIC), 2015 IEEE 15th International Conference on
Conference_Location :
Rome
Print_ISBN :
978-1-4799-7992-9
Type :
conf
DOI :
10.1109/EEEIC.2015.7165460