Abstract :
This study presents a new methodology based on risk/investment to solve transmission network expansion planning (TNEP) problem with multiple future scenarios. Three mathematical models related to TNEP problems considering multiple future generation and load scenarios are also presented. These models will provide planners with a meaningful risk assessment that enable them to determine the necessary funding for transmission lines at a permissible risk level. The results using test and real systems show that the proposed method presents better solutions compared with scenario analysis method.
Keywords :
power transmission lines; power transmission planning; risk management; mathematical models; risk assessment; risk/investment-driven transmission expansion planning; transmission lines; transmission network expansion planning;
fLanguage :
English
Journal_Title :
Generation, Transmission & Distribution, IET
Publisher :
iet
ISSN :
1751-8687
Type :
jour
DOI :
10.1049/iet-gtd.2011.0742
Filename :
6519367
Link To Document :
بازگشت