DocumentCode :
771835
Title :
Chronological probabilistic production costing and wheeling calculations with transmission network modeling
Author :
Pereira, M.V.F. ; Gorenstin, B.G. ; Fo, M. Morozowski ; Silva, J.B.
Author_Institution :
CEPEL, Rio de Janeiro, Brazil
Volume :
7
Issue :
2
fYear :
1992
fDate :
5/1/1992 12:00:00 AM
Firstpage :
885
Lastpage :
891
Abstract :
The authors present an approach for the integrated analysis of generation and transmission system in terms of production costing and wheeling rate calculations. The methodology is based on the chronological simulation of system operation. Economic dispatch at each state is provided by linearized optimal power flow routines, which can represent network aspects and export/import contracts among utilities. Probabilistic aspects are represented by Monte Carlo sampling of generation capacities, load levels, etc. Marginal costs are calculated at bus level and serve as a basis for the evaluation of wheeling rates. This makes it possible to model complex utility situations for use in power system planning and operations, determination of interchange contracts, and regulatory applications
Keywords :
Monte Carlo methods; economics; electric power generation; load flow; power system planning; transmission network calculations; Monte Carlo sampling; bus level marginal costs; chronological simulation; economic dispatch; export/import contracts; generation capacities; interchange contracts; linearized optimal power flow; load levels; power system planning; probabilistic production costing; production costing; regulatory applications; system operation; transmission network modeling; wheeling calculations; Capacity planning; Contracts; Costing; Costs; Load flow; Monte Carlo methods; Power generation economics; Power system economics; Power system modeling; Production systems;
fLanguage :
English
Journal_Title :
Power Systems, IEEE Transactions on
Publisher :
ieee
ISSN :
0885-8950
Type :
jour
DOI :
10.1109/59.141800
Filename :
141800
Link To Document :
بازگشت