Special design and testing aspects of the 345 kV East Fishkill substation
Author :
Fogarty, R.P. ; Halleran, T.M. ; Laskowski, L.M. ; Mark, D.A.
Author_Institution :
Consolidated Edison Co. of New York, NY, USA
Volume :
7
Issue :
4
fYear :
1992
fDate :
10/1/1992 12:00:00 AM
Firstpage :
1993
Lastpage :
2001
Abstract :
The installation of two 135 MVAr capacitor banks in a 345 kV substation required special design of the grounding system, installation of reactors in series with the capacitor banks, closing resistors in the circuit breakers and special shielding of control cables. The authors present some of the special problems encountered in the design of the substation and the results of the tests performed during commissioning of the capacitor banks
Keywords :
capacitor storage; earthing; reactors (electric); substations; testing; 135 MVAr; 345 kV; East Fishkill substation; capacitor banks; circuit breakers; closing resistors; control cables shielding; grounding system; reactors; testing; Cables; Capacitors; Circuit breakers; Circuit testing; Control systems; Grounding; Inductors; Performance evaluation; Resistors; Substations;
fLanguage :
English
Journal_Title :
Power Delivery, IEEE Transactions on
Publisher :
ieee
ISSN :
0885-8977
Type :
jour
DOI :
10.1109/61.157003
Filename :
157003
Link To Document :
بازگشت