Closure on "A new method for real-time monitoring of high voltage transmission line conductor sag"
Author
Olsen, R.G. ; Edwards, K.S.
Author_Institution
Sch. of Electr. Eng. & Comput. Sci., Washington State Univ., Pullman, WA, USA
Volume
18
Issue
4
fYear
2003
Firstpage
1598
Lastpage
1599
Abstract
The authors reply to the comments by Y Moltis (see ibid., vol.18, n0.4, p.1597-8, 2003) on their original paper (see ibid., vol.17, p.1142-52, 2002). The authors respond to the questions and points raised by Moltis on the feasibility of using the method on 500 kV lines, the use of resistive wires, conductor stringing, and clearance critical spans.
Keywords
monitoring; overhead line mechanical characteristics; clearance critical spans; conductor stringing; high voltage transmission line conductor sag; real-time monitoring; resistive wires; Arc discharges; Conductors; Monitoring; Optical fiber cables; Power cables; Power system reliability; Power transmission lines; Transmission lines; Voltage; Wire;
fLanguage
English
Journal_Title
Power Delivery, IEEE Transactions on
Publisher
ieee
ISSN
0885-8977
Type
jour
DOI
10.1109/TPWRD.2003.817762
Filename
1234741
Link To Document