Setting Test Intervals and Allowable Bypass Times as a Function of Protection System Goals
Author :
Hirsch, Herbert M.
Author_Institution :
General Electric Company San Jose, California
Abstract :
This analysis demonstrates the usefulness of availability design goals for determining required periodic test intervals and allowable bypass times as permitted by IEEE-279 criteria. Formulas are developed for calculating these times for instrumentation logic configurations common to reactor protection systems. Both simultaneous and uniformly staggered test schedules are considered. In addition to sample problems illustrating the application of these formulas, nomographs are presented for rapid graphical determination of test intervals and bypass times.
Keywords :
Availability; Calibration; Inductors; Logic testing; Nuclear power generation; Power system protection; Reactor instrumentation; Safety; Sections; System testing;