    The Tennessee Valley Authority´s (TVA´s) experience and action plans with freestanding oil-filled current transformers (CTs)

  • Author

    Boyle, John R. ; Cummings, Harold ; Arp, Barry

  • Author_Institution
    Tennessee Valley Authority, Chattanooga, TN, USA
  • Volume
    3
  • Issue
    4
  • fYear
    1988
  • fDate
    10/1/1988 12:00:00 AM
  • Firstpage
    1769
  • Lastpage
    1775
  • Abstract
    Historical background data are provided on current transformer (CT) failures, and some initial, unsuccessful attempts to correct the problem are discussed. Attempts to detect incipient failures by sampling the oil periodically revealed the weaknesses and hazards in the initial program. A task force was established to develop safety procedures that would minimize hazards to personnel working in the areas of suspect oil-filled CTs. The task force also developed an online monitoring device that detects incipient failures so that CTs can be removed from service before catastrophic failures occur
  • Keywords
    automatic test equipment; current transformers; failure analysis; insulating oils; transformer insulation; CT failures; Tennessee Valley Authority; failure detection; freestanding oil-filled current transformers; hazards; incipient failures; online monitoring device; Condition monitoring; Explosives; Hazards; Manufacturing; Personnel; Petroleum; Safety; Semiconductor device manufacture; Senior members; Voltage;