• DocumentCode
    991413
  • Title

    "Synchronized at the load\´\´-II Calculations of system performance

  • Author

    Griscom, S.B.

  • Author_Institution
    General Engineer, Westinghouse Elee. and Mfg. Co., East Pittsburgh, Pa.
  • Volume
    48
  • Issue
    4
  • fYear
    1929
  • Firstpage
    1083
  • Lastpage
    1092
  • Abstract
    This paper describes the results of calculations made for operating the Hell Gate and Sherman Creek generating stations of the United Electric Light and Power Company synchronized at the load. After reducing the numerous branches of the system to a simpler equivalent, calculations were made on the operation of an isolated section. These calculations indicated ample static stability and transient stability under fault conditions representing the maximum which might normally be expected. Other calculations were made indicating that the entire system, with synchronizing paths completed through the substation low-voltage busses would likewise meet the required stability conditions. Tentative system design factors, based on the calculations and experience to date, are suggested as a guidle to system planning. This paper shows a practical application of the theories and principles developed in the studies of transmission stability. In the present case a somewhat different object was in view inasmuch as it was desired to substantiate ideas as to the feasibility of the plan of synchronizing at the load, rather than to obtain numerical limits.
  • Keywords
    Circuit stability; Inductors; Joining processes; Power generation; Power supplies; Power system reliability; Power system stability; Power system transients; Substations; System performance;
  • fLanguage
    English
  • Journal_Title
    American Institute of Electrical Engineers, Transactions of the
  • Publisher
    ieee
  • ISSN
    0096-3860
  • Type

    jour

  • DOI
    10.1109/T-AIEE.1929.5055357
  • Filename
    5055357