Operating Experience with Automatic Equipment on an Edison System
Author :
Wyatt, F.D.
Author_Institution :
Electrical Engineer, Union Gas & Electric Co., Cincinnati, Ohio.
fYear :
1924
Firstpage :
768
Lastpage :
775
Abstract :
The paper describes the conversion equipment serving the Edison System in Cincinnati and the application of automatic machines and controls to that system. During two years´ operating experience with automatic equipment, it was found to be very reliable and to operate much quicker than manually-controlled equipment. Tests on the automatic equipment show it to be very valuable for service restoration work.
Keywords :
Automatic control; Automatic testing; Batteries; Control systems; Reliability engineering; Substations; Synchronous generators; System testing;
fLanguage :
English
Journal_Title :
American Institute of Electrical Engineers, Transactions of the
Publisher :
ieee
ISSN :
0096-3860
Type :
jour
DOI :
10.1109/T-AIEE.1924.5061033
Filename :
5061033
Link To Document :
بازگشت