Title :
Study of primary networks at pittsburgh
Author :
Holben, W. P. ; Lange, J. E.
Author_Institution :
Duquesne Light Company, Pittsburgh, Pa.
Abstract :
THE 4-KV PRIMARY NETWORK type of distribution system has been used successfully in the Pittsburgh area since 1931, when the Verona-Oakmont network was placed in service. A new 4-kv primary network installation for the Squirrel Hill area has been installed utilizing the modern equipment that is now offered by manufacturers.
Keywords :
Circuit breakers; Circuit faults; Oil insulation; Power cables; Regulators; Substations; Wires;
Journal_Title :
Electrical Engineering
DOI :
10.1109/EE.1949.6443283