Abstract
In this paper economic analysis of investment decisions and outage costs is given. The methods to determine outage costs in distribution company´s viewpoint are presented. The effects of regulation are taken into account in cost valuating process. The paper also present methods to compose interruption costs using actual interruption data and customer interruption costs (CIC) of Finnish distribution business. The methods make it possible to define outage costs even if there is no customer-specific interruption statistics available. Examples from actual network are presented when outage costs are modeled using secondary substation-specific, company-specific or nationwide cost parameters.
Keywords
costing; investment; power supply quality; power system economics; Finnish distribution business; actual interruption data; company-specific parameters; customer interruption costs; economic analysis; interruption costs; investment decisions; nationwide cost parameters; outage costs parameters; secondary substation-specific parameters; Agriculture; Companies; Costs; Customer service; Investments; Power generation economics; Power quality; Regulators; Statistical distributions; Voltage;
fLanguage
English
Publisher
ieee
Conference_Titel
Power Engineering Society General Meeting, 2005. IEEE
Print_ISBN
0-7803-9157-8
Type
conf
DOI
10.1109/PES.2005.1489220
Filename
1489220
Link To Document