Iowa Electrical Light & Power Company´s Duane Arnold Energy Center (DAEC) completed surface enhancement of all control-room panels. This resolved a majority of the human engineering deficiencies (HEDs) identified during the Detailed Control Room Design Review (DCRDR) study. Operations staff involvement and emphasis on providing functional changes resulted in operational effectiveness. Procedure modifications were incorporated simultaneously with the changes to minimize the introduction of additional new HEDs. It was concluded that operator response was overwhelmingly positive to the accomplished refinement of the man-machine interface.<>
Keywords :
control facilities; human factors; user interfaces; Detailed Control Room Design Review; Duane Arnold Energy Center; control room panels; human engineering deficiencies; man-machine interface; operator response; surface enhancements; Costs; Cyclic redundancy check; Disaster management; Energy resolution; Ergonomics; Human factors; Lighting control; Power engineering and energy; Switches; Transient analysis;
Conference_Titel :
Human Factors and Power Plants, 1988., Conference Record for 1988 IEEE Fourth Conference on
Conference_Location :
Monterey, CA, USA
DOI :
10.1109/HFPP.1988.27500