DocumentCode
17831
Title
Reserve Power Arrangements in Rural Area Underground Cable Networks
Author
Haakana, Juha ; Kaipia, Tero ; Lassila, Jukka ; Partanen, Jarmo
Author_Institution
Dept. of Electr. Eng., Lappeenranta Univ. of Technol., Lappeenranta, Finland
Volume
29
Issue
2
fYear
2014
fDate
Apr-14
Firstpage
589
Lastpage
597
Abstract
The popularity of underground cables to replace overhead lines is increasing. This is partly a consequence of the requirement for better reliability and supply security. In some countries, the authorities have set maximum interruption durations for distribution system operators to steer the operators to avoid the use of overhead lines. However, although faults are typically of a rare occurrence in underground cable networks, they cannot be completely avoided. Since the fault repair process in an underground cable network is time consuming, the distribution network should be meshed, and the rate of disconnecting switches should be high enough. However, this is not always possible or economically feasible and, therefore, other opportunities to restore the electricity supply should also be considered. This is especially the case for branch lines without a backup option. Yet, the power should be restored in a reasonable amount of time, which emphasizes the significance of an appropriate switch placement strategy and reserve power planning. This paper proposes a methodology to analyze the costs of different reserve power strategies and to optimize the reserve power arrangements. The reserve power strategies under consideration are the application of reserve power cables and reserve power generators and looping of the existing branch lines.
Keywords
fault location; optimisation; power distribution faults; power distribution planning; power distribution protection; power distribution reliability; power system restoration; power system security; switches; underground cables; branch lines loop; disconnected switches; distribution network; distribution system operators; electricity supply restoration; fault repair process; power supply security; reliability; reserve power arrangement optimization; reserve power cables; reserve power generators; reserve power planning; rural area underground cable network; switch placement strategy; Electricity; Generators; Interrupters; Maintenance engineering; Power cables; Reliability; Substations; Branch line; electricity distribution; reserve power; strategic planning; switch placing;
fLanguage
English
Journal_Title
Power Delivery, IEEE Transactions on
Publisher
ieee
ISSN
0885-8977
Type
jour
DOI
10.1109/TPWRD.2013.2280041
Filename
6605546
Link To Document