    Faults in energy systems and short-term or long-term loss of electricity are inevitable. Fixing the system and energizing distribution network afterward is a time consuming process. While the system is not online, the "energy not supplied" is increased. This event can cause the system to operate in non-reliable condition and endure damages and expenses, to both consumers and utilities. In this paper, a simple method is developed and discussed for decreasing the duration of the system restoration process by optimal placement of maintenance crews. To assign the locations, the effects of environmental phenomena, economical and technical constrains are considered. This method is used to determine the optimal locations for establishment of crews in Mahneshan County of Zanjan/Iran province.
  • Keywords
    distribution networks; maintenance engineering; power distribution reliability; Iran; Zanjan; electricity loss; energy systems; maintenance crew placement; reliable distribution network; Decision support systems; Environmental economics; Fuses; Geographic Information Systems; Maintenance; Power generation economics; Power system management; Power system protection; Power system reliability; Substation protection;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Power and Energy Engineering Conference (APPEEC), 2010 Asia-Pacific
  • Conference_Location
    Chengdu
  • Print_ISBN
    978-1-4244-4812-8
  • Electronic_ISBN
    978-1-4244-4813-5
  • Type

    conf

  • DOI
    10.1109/APPEEC.2010.5448154
  • Filename
    5448154