DocumentCode :
2322968
Title :
External insulation operation experience of ±500 kV Gezhouba-Nanqiao HVDC project
Author :
Zhiyi, Su ; Zhaoying, Sun
Author_Institution :
Electr. Power Res. Inst., Beijing, China
Volume :
1
fYear :
1998
fDate :
18-21 Aug 1998
Firstpage :
538
Abstract :
The operation condition of the external insulation of the converter stations and transmission lines of China´s ±500 kV Gezhouba-Nanqiao HVDC project was surveyed and analysed. The reasons of the flashover and damage of DC bushings and insulators were discussed. Some suggestions for the safe operation of HVDC equipment were advanced
Keywords :
HVDC power convertors; HVDC power transmission; electric breakdown; flashover; insulators; power transmission lines; project engineering; substation insulation; 500 kV; China; DC bushings; Gezhouba-Nanqiao HVDC project; HVDC equipment safety; converter stations; damage; external insulation; flashover; insulators; operating experience; transmission lines; Capacitors; Dielectrics and electrical insulation; Flashover; HVDC transmission; Insulators; Pollution measurement; Programmable control; Rain; Surface contamination; Voltage;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Power System Technology, 1998. Proceedings. POWERCON '98. 1998 International Conference on