Abstract :
This paper introduces the logical "next step" in the evolution of P&C implementation a bridge between today\´s conventional substation and tomorrow\´s IEC 61850 substation. It will introduce the concept of application building using a library of discrete software protection, control, communication, and logic function blocks that are based upon the IEC 61850 logical node. Using a graphical user interface tool the user can optimally build applications and place functionality in appropriately sized and located (distributed) substation IEDs. In addition, the P&C applications that are built may be applied in conventional or IEC 61850 environments or somewhere in between. The paper will also address P&C application testing and testing responsibilities, P&C functionality distributed among the IEDs used in the substation, and finally provide some examples of available P&C solutions.
Keywords :
IEC standards; distributed processing; graphical user interfaces; power engineering computing; substation automation; substation protection; IEC 61850 logical node; P&C implementation; discrete software protection; distributed substation IED; graphical user interface tool; logic function blocks; power system control; power system protection; Application software; Bridges; Communication system control; Graphical user interfaces; IEC standards; Logic functions; Software libraries; Software protection; Substation protection; Testing;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Protective Relay Engineers, 2010 63rd Annual Conference for
Conference_Location :
College Station, TX
Print_ISBN :
978-1-4244-6073-1
Type :
conf
DOI :
10.1109/CPRE.2010.5469522
Filename :
5469522
Link To Document :
بازگشت