Calculating critical degree of the path in a project network with fuzzy activity duration
Author :
Hongxiang Ouyang ; Yinghui Jian
Author_Institution :
Bus. Sch., Hohai Univ., Nanjing, China
fYear :
2011
fDate :
8-11 Jan. 2011
Firstpage :
86
Lastpage :
88
Abstract :
In traditional CPM/PERT technique, activity duration must be represented either as crisp number or as random variable drawn from certain probability distribution. However, it is usually difficult to define and estimate precisely the operation time for each activity in a real situation. Based on the liner programming and Zadeh´s extension principle, this paper presents a method for measuring critical degree of the path in a project network with fuzzy activity times. In the last, this paper uses matlab language to program, and verifies its feasibility and simplicity by an example.
Keywords :
PERT; critical path analysis; fuzzy set theory; linear programming; statistical distributions; CPM; PERT; Zadeh extension principle; critical path method; fuzzy activity duration; linear programming; matlab language; probability distribution; Educational institutions; Indexes; Mathematical model; Operations research; Probability distribution; Programming; critical path; fuzzy PERT; project management;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Management Science and Industrial Engineering (MSIE), 2011 International Conference on
Conference_Location :
Harbin
Print_ISBN :
978-1-4244-8383-9
Type :
conf
DOI :
10.1109/MSIE.2011.5707528
Filename :
5707528
Link To Document :
بازگشت