Monte carlo simulation algorithm research taking account for substation elements connection in bulk electric system
Author :
Wang, Yong ; Han, Xueshan ; Ding, Ying
Author_Institution :
Sch. of Electr. Eng., Shandong Univ., Jinan, China
fYear :
2009
fDate :
6-7 April 2009
Firstpage :
1
Lastpage :
4
Abstract :
Based on the conventional Monte-Carlo simulation algorithm, this paper considers the primary elements connection in the substation. By means of topology analysis algorithm, the substation elements connection analysis is completed first and the logical nodes and the connectivity between logical nodes and lines are determined. Then, the equal calculating model for network is presented. Meanwhile, after the simulation of elements faults, the protection and switching operation simulation is carried out.
Keywords :
Monte Carlo methods; switching substations; topology; Monte Carlo simulation algorithm; bulk electric system; logical nodes; substation elements connection analysis; switching operation simulation; topology analysis; Algorithm design and analysis; Analytical models; Computational modeling; Load flow; Network topology; Power system analysis computing; Power system modeling; Power system simulation; Sampling methods; Substations; Monte Carlo simulation; optimal power flow; switching operation; topology analysis;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Sustainable Power Generation and Supply, 2009. SUPERGEN '09. International Conference on
Conference_Location :
Nanjing
Print_ISBN :
978-1-4244-4934-7
Type :
conf
DOI :
10.1109/SUPERGEN.2009.5347954
Filename :
5347954
Link To Document :
بازگشت