Abstract
Protection performance is dependent on the availability of accurate and reliable protection relays and their connection to high quality measuring transformers and well designed tripping systems. But it is only in the substation that all elements of protection systems are brought together during site installation and hence can be tested for the first time. The author describes the re-examination of on site testing requirements and methods undertaken during CEGB reorganisation. He shows that the introduction of new technology and increasing system utilisation factor has been fully taken into account
Keywords
power system protection; substations; switchgear testing; 275 kV; 400 kV; on site testing; power system protection; protection relays; substations; switchgear testing; tripping systems; utilisation factor;
fLanguage
English
Publisher
iet
Conference_Titel
Developments in Power Protection, 1989., Fourth International Conference on
Conference_Location
Edinburgh
Type
conf
Filename
20606
Link To Document