Abstract :
This paper presents a multi-stage approach for maintenance scheduling of generating units by simulated annealing. The maintenance procedures are classified into three types differing in outage duration. In the first stage of the scheduling, feasible combinations of maintenance schedule are sought by iterative application of simulated annealing. In the second stage, introduction of minor maintenance is determined to maintain the required reserve rate. In the third stage, based on the feasible mix of maintenance schedule, a global optimum solution is attained by simulated annealing. The effectiveness of the proposed approach was evaluated by a practical size model analysis and comparison with the enumeration method
Keywords :
boilers; iterative methods; maintenance engineering; operations research; simulated annealing; thermal power stations; iterative method; maintenance scheduling; multiple stage method; neighbourhood solutions; reserve rate; simulated annealing; thermal generating unit; Boilers; Maintenance; Optimal scheduling; Power generation; Power system modeling; Power system reliability; Power system simulation; Processor scheduling; Simulated annealing; Turbines;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Systems, Man, and Cybernetics, 1996., IEEE International Conference on
Conference_Location :
Beijing
ISSN :
1062-922X
Print_ISBN :
0-7803-3280-6
Type :
conf
DOI :
10.1109/ICSMC.1996.571374
Filename :
571374
Link To Document :
بازگشت