DocumentCode
3691420
Title
Design and testing of a 900 kW, 140 GHz gyrotron
Author
Stephen Cauffman;Monica Blank;Philipp Borchard;Kevin Felch
Author_Institution
Communications &
fYear
2015
Firstpage
1
Lastpage
2
Abstract
A 140 GHz gyrotron capable of producing output powers up to 900 kW for 1000-second pulses has been developed at CPI. Factory testing demonstrated 1000-second operation at the 25 A CW current limit of the test facility, at which the output power was about 500 kW, and demonstrated 900 kW operation for short pulses. The gyrotron was then shipped to Hefei, China, and installed as part of the electron cyclotron heating and current drive system for the EAST tokamak. Commissioning of the gyrotron at the EAST site is currently in progress, with the goal of demonstrating operation at full parameters (900 kW for 1000-second pulses).
Keywords
"Gyrotrons","Testing","Superconducting magnets","Power generation","Production facilities","Tokamaks","Cavity resonators"
Publisher
ieee
Conference_Titel
Infrared, Millimeter, and Terahertz waves (IRMMW-THz), 2015 40th International Conference on
ISSN
2162-2027
Electronic_ISBN
2162-2035
Type
conf
DOI
10.1109/IRMMW-THz.2015.7327573
Filename
7327573
Link To Document