• DocumentCode
    39565
  • Title

    Commissioning of the Main Coil of the EDIPO Test Facility

  • Author

    Bruzzone, Pierluigi ; March, Stephen ; Croari, Giancarlo ; Jenni, M. ; Uglietti, D. ; Stepanov, Boris ; Wesche, Rainer ; Vogel, M. ; Portone, A. ; Cau, F.

  • Author_Institution
    Centre de Rech. en Phys. des Plasmas (CRPP), Fusion Technol., Ecole Polytech. Fed. de Lausanne, Lausanne, Switzerland
  • Volume
    24
  • Issue
    3
  • fYear
    2014
  • fDate
    Jun-14
  • Firstpage
    1
  • Lastpage
    5
  • Abstract
    The EDIPO test facility is erected at CRPP Villigen with the aim of providing a flexible, high field test bed for high current force flow superconductors. The EDIPO main coil is a tilted-head race-track pair wound by a graded Nb3Sn cable-in-conduit conductor. The whole project, partly funded by the European Commission, started in 2004 and entered the commissioning phase in 2013. The final steps of instrumentation and installation of the main coil, delivered by industry in May 2011, lasted about 18 months. The first cool-down of the facility started in November 2012. The commissioning of the main coil, including the precise measurement of the generated magnetic field, was carried out in March 2013. At an operating current of 17.2 kA, a ± 1% homogenous field of 12.35 T was generated over a length of 900 mm in the center of the test well, 140 mm × 91 mm in cross section. Details about cool-down, flux jumps, forces and displacements, field map, and charging rate are presented in this paper.
  • Keywords
    commissioning; niobium alloys; superconducting coils; tin alloys; EDIPO main coil; EDIPO test facility; Nb3Sn; charging rate; commissioning phase; cool-down; field map; flexible high field test bed; flux jumps; graded cable-in-conduit conductor; high current force flow superconductors; homogenous field; instrumentation; magnetic field measurement; main coil commissioning; main coil installation; operating current; tilted-head race-track pair; Assembly; Coils; Conductors; Cooling; Flanges; Temperature measurement; Test facilities; ${rm Nb}_{3}{rm Sn}$ cable-in-conduit conductor; Commissioning; high field magnet; test facility;
  • fLanguage
    English
  • Journal_Title
    Applied Superconductivity, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    1051-8223
  • Type

    jour

  • DOI
    10.1109/TASC.2013.2284721
  • Filename
    6620998