DocumentCode
403368
Title
Summary of the SERC generator modeling validation task force (GMVTF)´s on-going development of a SERC supplement to NERC planning standard II.B. (system modeling data requirements - generation equipment)
Author
Schaeffer, Carsten
Volume
3
fYear
2003
fDate
13-17 July 2003
Firstpage
1323
Abstract
The SERC Engineering Committee commissioned a task force of generator operators and transmission planners, the generator modeling validation task force (GMVTF), to develop such a procedure/supplement of recommended validation practices to ensure that generator dynamic models are maintained consistent with field equipment conditions. The paper presents the draft supplement in which the GMVTF is approaching or has reached a consensus. Also, the draft supplement in which the GMVTF has not fully discussed or has not reached a consensus is also presented.
Keywords
electric generators; standards; NERC planning standard II B; SERC Engineering Committee; generation equipment; generator dynamic models; generator modeling validation task force; generator operators; system modeling data requirements; transmission planners; validation practices; Character generation; Data engineering; Meeting planning; Modeling; Power engineering and energy; Power generation; Power system planning; Standards development; Testing; Virtual manufacturing;
fLanguage
English
Publisher
ieee
Conference_Titel
Power Engineering Society General Meeting, 2003, IEEE
Print_ISBN
0-7803-7989-6
Type
conf
DOI
10.1109/PES.2003.1267340
Filename
1267340
Link To Document