• DocumentCode
    403368
  • Title

    Summary of the SERC generator modeling validation task force (GMVTF)´s on-going development of a SERC supplement to NERC planning standard II.B. (system modeling data requirements - generation equipment)

  • Author

    Schaeffer, Carsten

  • Volume
    3
  • fYear
    2003
  • fDate
    13-17 July 2003
  • Firstpage
    1323
  • Abstract
    The SERC Engineering Committee commissioned a task force of generator operators and transmission planners, the generator modeling validation task force (GMVTF), to develop such a procedure/supplement of recommended validation practices to ensure that generator dynamic models are maintained consistent with field equipment conditions. The paper presents the draft supplement in which the GMVTF is approaching or has reached a consensus. Also, the draft supplement in which the GMVTF has not fully discussed or has not reached a consensus is also presented.
  • Keywords
    electric generators; standards; NERC planning standard II B; SERC Engineering Committee; generation equipment; generator dynamic models; generator modeling validation task force; generator operators; system modeling data requirements; transmission planners; validation practices; Character generation; Data engineering; Meeting planning; Modeling; Power engineering and energy; Power generation; Power system planning; Standards development; Testing; Virtual manufacturing;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Power Engineering Society General Meeting, 2003, IEEE
  • Print_ISBN
    0-7803-7989-6
  • Type

    conf

  • DOI
    10.1109/PES.2003.1267340
  • Filename
    1267340