DocumentCode :
539373
Title :
Throughput improvement with setup reduction focusing on process identification
Author :
Kobayashi, Yoshiaki ; Hayamizu, Taichi ; Sakai, Katsuhisa
Author_Institution :
Renesas Technology Corp., 751, Horiguchi, Hitachinaka-shi, Ibaraki-ken, 312-8504, Japan
fYear :
2008
fDate :
27-29 Oct. 2008
Firstpage :
107
Lastpage :
110
Abstract :
We improved throughput by reducing operational loss that occurs owing to the process condition change in semiconductor manufacturing equipments. As a result of Equipment Engineering System (EES) data analysis, we found that it took time from several to ten percent of Raw Processing Time to adjust etchers Electrostatic Chuck (ESC) temperature. Controlling ESC temperature of each recipe based on process flow and process information, and processing the same ESC temperature process consecutively for a certain period have resulted in throughput improvement in etching process by up to 7 percent and by 4 percent on average.
Keywords :
Dispatching; Etching; Manufacturing; Process control; Productivity; Temperature measurement; Throughput;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Semiconductor Manufacturing (ISSM), 2008 International Symposium on
Conference_Location :
Tokyo, Japan
ISSN :
1523-553X
Electronic_ISBN :
1523-553X
Type :
conf
Filename :
5714894
Link To Document :
بازگشت