Title :
The Rockport plant-analysis of temporary fast turbine valving tests
Author :
Pasternack, B.M. ; Bhatt, N.B.
Author_Institution :
American Electric Power Service Corp., Columbus, OH, USA
fDate :
5/1/1988 12:00:00 AM
Abstract :
Temporary fast turbine valving (TFTV) field tests were carried out on AEP´s 1300 MW Rockport unit. Tests at various unit loading levels verified the functional aspects of the TFTV scheme, including the control and intercept valve-stroke characteristics and the rapid reduction of mechanical driving power. An analysis of the mechanical and electrical performance characteristics of the Rockport unit during TFTV is presented. A comparison of the test measurements with digital simulation results is provided to validate the simulation tools and models commonly used in system dynamics studies
Keywords :
digital simulation; electrical engineering computing; power stations; turbines; 1300 MW; Rockport plant; control; digital simulation; electrical performance; intercept valve-stroke characteristics; mechanical driving power; simulation tools; temporary fast turbine valving tests; Boilers; Packaging; Power system planning; Power system stability; Power system transients; Relays; Senior members; System testing; Turbines; Valves;
Journal_Title :
Power Systems, IEEE Transactions on