A reliability-based approach to transmission maintenance planning and its application in BC hydro system
Author
Li, Wenyuan ; Korczynski, Jerry
Author_Institution
Syst. Performance Assessment Div., British Columbia Transmission Corp., Vancouver, BC, Canada
Volume
19
Issue
1
fYear
2004
Firstpage
303
Lastpage
308
Abstract
This paper presents a reliability-based method for transmission maintenance planning. A quantified impact assessment of the planned outage on operation reliability of the whole transmission system is a main feature of the proposed method. This reliability centered maintenance (RCM) approach for transmission systems provides not only the lowest risk maintenance schedule but also the most reliable operation mode for the planned outage. Another feature of the method is ease of incorporation into the existing traditional transmission maintenance procedure. A time-shift-based Monte Carlo simulation technique and a linear programming optimization model are used to perform reliability evaluation of the transmission system with planned outage(s). An example for the planned replacement of a 230-kV cable in the BC Hydro North Metro system has been given to demonstrate a practical application of the proposed procedure and the method.
Keywords
Monte Carlo methods; hydroelectric power stations; linear programming; maintenance engineering; power transmission planning; power transmission reliability; 230 kV; BC Hydro North Metro system; linear programming optimization model; operation reliability; reality-based approach; reliability centered maintenance; time-shift based Monte Carlo simulation; transmission maintenance planning; Costs; Helium; Linear programming; Maintenance; Performance evaluation; Power cables; Power system planning; Power system reliability; Scheduling; Transient analysis;
fLanguage
English
Journal_Title
Power Delivery, IEEE Transactions on
Publisher
ieee
ISSN
0885-8977
Type
jour
DOI
10.1109/TPWRD.2003.820183
Filename
1256392
Link To Document