• DocumentCode
    976218
  • Title

    Hydro turbine-governor model validation in pacific northwest

  • Author

    Kosterev, Dmitry

  • Author_Institution
    Transmission Operations & Planning, Bonneville Power Adm., Vancouver, WA, USA
  • Volume
    19
  • Issue
    2
  • fYear
    2004
  • fDate
    5/1/2004 12:00:00 AM
  • Firstpage
    1144
  • Lastpage
    1149
  • Abstract
    This paper presents an approach for generator model validation based on the measurements taken at the point of interconnection. The approach is initially applied for The Dalles powerhouse, where the simulated and actual governor responses were found different. Governor tests and monitoring were performed and resulted in model revisions. The approach also resulted in improvements of John Day turbine-governor models. Grand Coulee governor response was validated and found adequate. Based on the project experience, a process for generator model validation is proposed.
  • Keywords
    hydraulic turbines; hydroelectric generators; monitoring; power system interconnection; power system simulation; Dalles powerhouse; John Day turbine-governor models; Pacific Northwest; disturbance monitoring; generator model validation; generator testing; grand Coulee governor response; hydro turbine-governor model validation; interconnection point; power system dynamic modeling; Councils; Frequency; Monitoring; Phasor measurement units; Power generation; Power system modeling; Power system reliability; Predictive models; Testing; Voltage;
  • fLanguage
    English
  • Journal_Title
    Power Systems, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0885-8950
  • Type

    jour

  • DOI
    10.1109/TPWRS.2003.821464
  • Filename
    1295026